Awarded
Puffin Produce Front End Factory Concrete Works Package
Descriptions
This tender publictation is seeking sub-contractor work: CONCRETE SLABS – the supply and placement of all materials associated with the concrete slabs construction, including all necessary plant and equipment to carry out the works, i.e. concrete, mesh, corrugated steel decking, shuttering/formwork, edge protection, access equipment, concrete pumps, power-floats & finishing tools/equipment etc. Sub-contractor to satisfy themselves that they have allowed for all necessary access and equipment in order to carry out the works including being aware of site conditions that may have an effect on completing the works to schedule as per programme attached.Note:•Sub-contractor welcome to include alternate design & costings in addition to pricing scheduled items•Minor engineering should be allowed for by the sub-contractor•Design coordination with the project Architect, Engineers & Cladding specialist•Sub-contractor should allow all necessary temporary access associated with the works•Site visit is compulsory to appreciate the clients existing working environment•Sub-contractor to allow for task lighting and power for the duration of their works•Sub-contractor to allow for material storage within price (as required)•Onsite WC and mess facilities are available ‘por gratis’Costs:Your lowest quotation is invited for the sub-contract work shown above inclusive of all Design, Labour, Plant and Materials, in accordance with the following documents: -Specification (pages) : Included on drawingsDrawings:Slab Info;Roger Casey Drawings: 19895-102_2018-03-20Roger Casey Drawings: 19895-201, 19895-202 & 19895-215 Preliminary-2018_04_03Powell Dobson Drawing: 17055 (P) 103Other Scheme Drawings;Roger Casey Drawings: 19895-01Roger Casey Drawings: 19895-100_2018-03-20Roger Casey Drawings: 19895-101_2018-03-20Roger Casey Drawings: 19895-203, 204, 205, 206, 210, 211 & 220Powell Dobson Drawing: 01 Cold Store SketchPowell Dobson Drawing: 17055 (P) 104, 105, 106, 107, 108, 109, 110, 111, 112, 113, 114 & 115.Powell Dobson Drawings: 17055 (SK) 003Powell Dobson Drawings: 17055 (EX) 01, 02 & 03Project Boundary Drawing – Amended PDA 17055 (P)101Other: Puffin 04 – Pictures 1, 2 and 4Timescale: Enquiry Programme attached, it is envisaged that out of hours works will be required and must be included within your rates.Subcontract Particulars: NoneFLUCTUATIONS: Fixed Price for DurationDAYWORK: Please identify your hourly (all-inclusive) rate for all labour and plant costs, together with %mark-up required to the nettDISCOUNT: Please clearly state within your quotation the main contractors discount being offeredBy submitting a quotation it is deemed that you have inspected the drawings and visited the site to obtain any relevant details. Extras will not be paid due to lack of knowledge of the site conditions or form of general construction details.Contract Conditions:Liquidated Damages -£2,000 per week or part thereofRectification Period-6 MonthsRetention Percentage-3%Contractor’s Insurance Cover-5,000,000Insurance Liability of Employer-10,000,000
Timeline
Published Date :
Deadline :
Tender Awarded :
Awarded date :
Contract Start :
Contract End :
Tender Regions
CPV Codes
45262311 - Concrete carcassing work
45262310 - Reinforced-concrete work
45262370 - Concrete-coating work
44114000 - Concrete
44114200 - Concrete products
45262350 - Unreinforced-concrete work
45262300 - Concrete work
44114250 - Concrete slabs
44114100 - Ready-mixed concrete
Keywords
concrete
ready‑mix concrete
structural concrete
building concrete
poured concrete
ready‑mixed concrete
pre‑mixed concrete
batch‑mixed concrete
load‑mixed concrete
concrete delivery
concrete products
precast concrete units
concrete slabs
manhole sections
concrete blocks
precast slabs
floor slabs
pavement slabs
ceiling slabs
concrete work
cast-in-place concrete
mass concrete placement
concrete slab pouring
in-situ concrete construction
structural concrete works
concrete foundation building
reinforced concrete pour
concrete framing
civil concrete works
reinforced-concrete work
RCC building
rebar concrete structure
structural RC framing
reinforced slab construction
concrete beam and column work
steel-concrete composite construction
high-strength reinforced concrete work
seismic RC structure build
concrete carcassing work
formwork installation
shuttering works
concrete formwork erection
formwork carpentry
casting molds installation
formwork removal
concrete casing support
structural formwork systems
formwork engineering
unreinforced concrete work
plain concrete pours
non‑reinforced slab construction
concrete base pouring
mass concrete installation
slab casting
concrete bedding
in‑situ plain concretework
simple concrete pours
concrete foundation build
concrete-coating work
concrete sealing
protective concrete coating
surface treatment of concrete
anti‑corrosion coating
concrete waterproofing coat
concrete paint application
decorative concrete finish
concrete overlay
concrete surface treatment
Tender Lot Details
2 Tender Lots
Workflows
Status :
Procedure :
Suitable for SME :
Nationwide :
Assign to :
Tender Progress :
Details
Notice Type :
Tender Identifier :
Tenderbase ID :
Low Value :
High Value :
Buyer Information
Name :
Procurement contact
Name :
Phone :
Email :
Possible Competitors
1 Possible Competitors