Closed

Greek Street, Stockport. Rail bridge Reconstruction - FRC Package

Descriptions

CMP2/1a Greek street carries the two lane Greek Street Roundabout over the five track electrified West Coast Main Line, in Stockport City Centre. Two Tracks run below the East Span with the three remaining tracks below the west span. The bridge was originally a tunnel but was reconstructed as an overbridge in 1958. The Two span Simply supported superstructure consists of precast post-tensioned prestressed concrete deck beams and in-situ reinforced concrete deck slabs. Gaps between the beams are formed by in-situ reinforced concrete. The intermediate support is provided by a reinforced concrete crosshead beam, columns and foundation slab. The deck beams are post-tensioned transversely. Parapets for the structure are comprised of brickwork. The bridge has a skew spans of 9.14m on the east and 13.99m on the west side, at angles of 13 degrees. The carriageway width varies from 9 to 13m due to the layout of the roundabout. Footways are provided adjacent to the north and south parapets of the structure, with varying widths. Trief Kerbing with a mounted pedestrian guardrail are present to separate pedestrians from the carriageway. Greek Street Bridge is a two span post tensioned structure in which the latest PTSI assessment concluded that the structure is understrength and overstressed. Engineering standard NR/CIV/025 has been used to manage the substandard structure in the short term with additional monitoring in place. Specific elements of concern included exposed concrete reinforcement which has begun to corrode on the deck soffit, seepage of water onto the soffit which will cause degradation to accelerate further. The most recent assessment report stated that the risk of failure was 'High' to 'Very High' and that deck replacement is required in 2025, otherwise the structure would need to be closed to road traffic until completely reconstructed, due to the overstress and deterioration it would not be safe to operate. The project proposal is to replace the existing bridge with a single span removing the central pier in a 21 day core possession in August 2025. This will require alterations to the existing OLE equipment that runs underneath the structure. The highway will also be closed for a significant period whilst construction works are undertaken to replace the bridge - circa 50 weeks. The deck construction works will commence once all beams are landed, connected and waterproofing membrane is installed. The sub-contractor will then be responsible for setting up all formwork and erecting steel re-inforcement (Opportunity to construct in cages may arise during design development, but please assume in-situ at this stage). Supply all associated concrete. Sub-contractor to then provide 2no. concrete pumps for duration of their pouring works. Sub-contractor to also finish concrete.

Timeline

Published Date :

5th Jul 2024 1 year ago

Deadline :

26th Jul 2024 1 year ago

Contract Start :

31st Jul 2025

Contract End :

31st Aug 2025

Tender Regions

Keywords

concrete

concrete framing

concrete work

concrete bedding

shuttering works

floor slabs

slab casting

mortar mixers

precast slabs

cement retarder

concrete slabs

manhole sections

mixer pump

ceiling slabs

shotcrete pump

concrete sealing

concrete overlay

concrete blocks

cement pump

RCC building

grout pump

concrete mixers

poured concrete

formwork removal

pavement slabs

mobile concrete pump

civil concrete works

reinforced-concrete work

portable concrete mixers

cement mixing machines

concrete placement pump

cement plasticizer

mortar accelerator

ready mixed concrete

concrete delivery

formwork engineering

batch mixed concrete

load mixed concrete

industrial mixer units

reinforced concrete pour

pipeline concrete pump

concrete casing support

mass concrete placement

plain concrete pours

concrete admixture

RC skeleton erection

RC structure erection

formwork carpentry

precast concrete units

concrete carcassing work

concrete base pouring

structural concrete

cast-in-place concrete

structural RC framing

anti corrosion coating

ready mix concrete

RC building framework

building concrete

rebar concrete structure

concrete slab pouring

pre mixed concrete

construction pump

concrete-coating work

concrete products

construction mixers

simple concrete pours

formwork installation

steel-concrete composite construction

concrete beam and column work

structural formwork systems

load-bearing concrete structure

protective concrete coating

structural concrete build

concrete surface treatment

pump for ready-mix concrete

unreinforced concrete work

concrete superstructure work

surface treatment of concrete

structural concrete works

reinforced concrete shell build

mass concrete installation

reinforced concrete structure build

concrete paint application

concrete waterproofing coat

concrete core construction

concrete frame construction

in-situ concrete construction

non reinforced slab construction

in situ plain concretework

reinforced slab construction

concrete foundation building

decorative concrete finish

high-strength reinforced concrete work

concrete formwork erection

high-pressure concrete pump

seismic RC structure build

concrete foundation build

casting molds installation

Let’s Get you Started ✍

Get to see all tender details more briefly

Already have an account ?

Workflows

Status :

Closed

Procedure :

N/A

Suitable for SME :

Yes

Nationwide :

No

Assign to :

Tender Progress :

0%

Details

Notice Type :

Tender

Tender Identifier :

IT-378-246-T: 2024 - 001

Tenderbase ID :

310724019

Low Value :

£100K

High Value :

£1000K

Buyer Information

Address :

Liverpool Merseyside , Merseyside , L13 0BQ

Website :

N/A

Procurement Contact

Name :

Tina Smith

Phone :

0151 252 3243

Email :

tina.smith@shared-ed.ac.uk