Closed
Manchester Airport Piling ECI
Request tender documents
Save your time. You just request and we will send you the available documents.
Request for bid service
Save your time. You just request and we will arrange tender related all available documents to bid writers for the best possible quote.
Descriptions
The planned introduction of longer train services to the Airport in response to future demand growth will mean that double stacking arrangements of trains as currently used will no longer be viable. Through the project's Delivery Steering Group, Northern and TransPennine Express have carried out analysis which has identified that additional platform capacity is needed at the airport in order to realise the full benefit of longer train services serving the airport. The scheme is part of a package of proposed measures in the Manchester area that are being designed/planned to boost capacity and resilience, emanating from the Cross Manchester Capacity and Reliability Improvement Study. Improving the operation of train services in the centre of Manchester and providing further capacity at Manchester Airport station, aligns with the strategic aims of Network Rail, TfGM, TfN and the wider industry. This project in in Tranche 1 of the Manchester and North West Transformation Programme (MNTP): A remodelling of the station at Manchester Airport, specifically a platform addition or extension of multiple platforms, or provision of a new turnback facility, will be essential to accommodate the planned implementation of longer rolling stock services. The redevelopment of these platforms will enable permissive working of two 6x24m (144m) trains, in two of the four platforms at the Airport Station. This will allow for the unaltered retention of all existing TOC services both originating and terminating at the Airport Station under 'double-stacking' conditions. Kier are seeking expressions of interest for early contractor engagement in relation to the piling works at Manchester Airport. The piling package will consist of a 350m contiguous pile retaining wall of 900mm diameter CFA piles to a depth of up to 18m. The ECI works shall consist of: - Piling Rig Type (We have currently assumed SR95) - Piling duration (No of piles per day) - Working area required around the rig due to site constraints - Understanding of key risks and mitigations to comply with Network Rail Standard NR/L3/CIV/0063 Issue 2 - Temporary Works requirements - Piling Matt - Working in the vicinity of buried services - Pile deflection - A review of any similar example projects & Lessons Learnt Intent to award ECI contract to support a main consultant designing these works and ultimately leading to the installation works.
Timeline
Published Date :
Deadline :
Contract Start :
Contract End :
Tender Regions
CPV Codes
44212400 - Piling
Keywords
piling
concrete piles
steel piles
bored piling
foundation piles
driven piles
pile foundations
pile foundation works
deep foundation systems
pile installations
Workflows
Status :
Procedure :
Suitable for SME :
Nationwide :
Assign to :
Tender Progress :
Details
Notice Type :
Tender Identifier :
Tenderbase ID :
Low Value :
High Value :