Awarded

Transpennine Route Upgrade Programme – York Electrical Control Room Relocation

Descriptions

Network Rail intends to award a contract via direct award under the Procurement Act 2023 to Siemens Mobility Limited.

The new TRU electrified route will need to be controlled from the York ECR and the existing integrated electrical control centre (IECC) cannot be expanded any further. This project is required to relocate the control room from its current location to a new proposed location.

RailCom Manager is the existing Supervisory Control and Data Acquisition (SCADA) system within the current York IECC and has been installed since 2013. The newly installed TRU electrical infrastructure will need to feed into the new, York ECR and align itself with the SCADA system operating in that location (RailCom).

Timeline

Published Date :

26th Nov 2025 Yesterday

Deadline :

N/A

Tender Awarded :

1 Supplier

Awarded date :

N/A

Contract Start :

N/A

Contract End :

N/A

Keywords

mechanical engineering installation

precision plant installation

heavy machinery integration

process equipment fitting

Tender Lot Details

2 Tender Lots

Let’s Get you Started ✍

Get to see all tender details more briefly

Already have an account ?

Workflows

Status :

Awarded

Procedure :

N/A

Suitable for SME :

N/A

Nationwide :

No

Assign to :

Tender Progress :

0%

Details

Notice Type :

Tender

Tender Identifier :

IT-378-246-T: 2024 - 001

Tenderbase ID :

310724019

Low Value :

£100K

High Value :

£1000K

Buyer Information

Address :

Liverpool Merseyside , Merseyside , L13 0BQ

Website :

N/A

Procurement contact

Name :

Tina Smith

Phone :

0151 252 3243

Email :

tina.smith@shared-ed.ac.uk

Possible Competitors

1 Possible Competitors